Billings Bypass Railroad Bridge Nearing Completion

Contractor Wadsworth Brothers Construction has begun paving up to the railroad bridge in Lockwood near Coulson road. The last of the concrete deck is scheduled to be poured this Thursday. (Courtesy photo)

Last week contractors working on the Billings Bypass Railroad Bridge started their final steps on the bridge that will connect Lockwood to the newly built Yellowstone River Bridge. According to District Administrator Michael Taylor, the contractor Wadsworth Brothers Construction will be pouring its final concrete for the bridge deck on October 24. The concrete deck will then need to cure for 30 days before the contractor will be able to groove the deck and install guardrails.  

The Billings Bypass Railroad Bridge is one of the read more