Lockwood sewer ready for new connections

by Evelyn Pyburn-originally published in the weekly Yellowstone County News print edition

Some residents in Lockwood will be able to begin connecting to the Lockwood sewer.

As part of the Lockwood Phase Two Sewer Project, a two-block area and the lines connecting it to mains will be completed by the end of this week, and Lockwood Water and Sewer District manager Mike Ariztia recommended the district board allow residents to begin installing connections.

During a meeting last Wednesday, the LWSD Board approved the idea.

Jill Cook, who is overseeing the sewer project on behalf of Morrison Maierle, said that construction workers report residents are always asking them how soon they can connect. LWSD assistant manager Tony Reed added that they come into the district office almost daily to ask the same question.

COP Construction is on schedule and expects to complete the second phase of the Lockwood sewer by the end of August, said Ariztia. He reported that areas along Peter Street, Greenwood, Juniper, Hickory, Hemlock and Nightingale are essentially complete and crews will be moving this week to Sunrise and Eagle Rock. Work is beginning on Becraft, said Ariztia, where the line is going in 20-feet deep.

Ariztia asked for and received approval from the board to update and loop water lines for portions of Piccolo and read more