NWE Plans New Transmission Line to Meet Growth Needs

NorthWestern Energy has announced plans to build an additional 230 kV transmission line that will serve customers in Yellowstone County and the region that will provide “critical” additional electric transmission capacity.

The 21-mile long line – expected to cost between $25 million and $30 million – will run from NorthWestern Energy’s existing Shorey Road substation and head northwest, ending at NorthWestern Energy’s existing Broadview substation. The project includes upgrades to the Broadview Substation and Shorey Road Substation, both north of the Billings Area with construction anticipated in 2027 and 2028.

Project siting and right-of-way acquisition is intended to begin in 2025 and construction of the new electric transmission line anticipated in 2027, to be completed within the next three years.

The line will be subject to the Montana Major Facilities Siting Act, which requires NorthWestern to file a public notice in area newspapers and with the Montana Department of Environmental Quality describing the … Read full story here by subscribing here. 

 

Please follow and like us: